A9: In Production
Freer – Preparatory work has been completed; new motor ordered; ready to connect to production soon
A6: In Production
Freer – Back in production after storm
A5: In Production
Freer – Back in production after storm
A1: Production on hold
Freer – Production on hold due to further maintenance works
All wells in the “DCRC” Oil Field back online
All repairs on the electrical works at the “DCRC” oil field have been completed, and all wells are now back online and in production. Our dedicated teams have worked tirelessly to restore operations to full capacity following the recent power outage caused by the storm. We appreciate your patience and understanding during this time and thank you for your continued support.
B2: In Production
Freer – Back in production after storm
B1: Production on hold
Freer – Preparatory work has been completed; ready to connect to production soon
A10: Production on hold
Freer – Preparatory work has been completed; ready to connect to production soon
A9: Production on hold
Freer – Preparatory work has been completed; new motor ordered; ready to connect to production soon
A8: In Production
Freer – Back in production after storm
A7: In Production
Freer – Back in production after storm
A6: Production on hold
Freer – Preparatory work has been completed, some new electricity pylons and laid lines. have been erected; ready to connect to production soon
A5: Production on hold
Freer – Preparatory work has been completed, and we have erected some new electricity pylons and laid lines. We are now ready to connect to production very soon.
A4: In Production
Freer – Electricity to new transfer water pump successfully hooked up; plan to install a surveillance camera; production up to about 10 bopd
A3: In Production
Freer – Back in production after storm
A2: In Production
Freer – Back in production after storm
A1: In Production
Freer – Back in production after storm
A4: Production up to around 10 bopd
Well A4’s production has surged to around 10 bopd thanks to a new water pump that’s now connected to electricity.
6 Wells Back Online; 4 Wells Soon…
Our teams have successfully brought six wells back online after completing all necessary preparatory work. This includes the installation of new electricity pylons and laid lines, ensuring a smooth connection to production.
Significant Progress Made in Restoring Production at “DCRC” Oil Field
Following the recent power outage caused by the storm, our dedicated teams have been working tirelessly to bring production back to full capacity at the “DCRC” oil field. Significant progress has been made in restoring operations.
Update on the RAW Energy Oil Field in South Texas
Following the recent power outage caused by the storm, our teams have been working diligently to restore production at the “DCRC” oil field.